[title] Assemble the Ball Joint Platform
-[* 1] From the 290mm IM Arm / Platform Sub-Assembly Pack, locate the Ball Joint Platform (70857), Ball Joints for IM Carriage/Platform (70855), (6) #4 x 3/8" sheet metal screws (30250), and (6) #4 SAE Flat Washers (30449). Set the rest of the parts from that pack aside for later use in Final Assembly.
+[* 1] From the 290mm IM Arm / Platform Sub-Assembly Pack (70871), locate the Ball Joint Platform (70857), (3) Ball Joints for IM Carriage/Platform (70855), (6) #4 x 3/8" sheet metal screws (30250), and (6) #4 SAE Flat Washers (30449). Set the rest of the parts from that pack aside for later use in Final Assembly.
[* 1] Install the joints onto each of the three sets of posts on the ball joint platform as shown.
[* 1] Install a #4 washer and #4 x 3/8" sheet metal screw into each post to secure the ball joints.
[* 1] Fully Tighten.